FEMA Debris Removal Contracts: Mistakes That Cost Reimbursement

After a storm, cities, counties and schools rush to clear debris. FEMA can pay back part of that cost through Public Assistance. But FEMA only pays when the contract follows federal rules. A real FEMA appeal shows what goes wrong. If you haul debris or manage disaster response work, these mistakes matter to you too.
The case
Hurricane Matthew hit Georgia in October 2016. It left trees and limbs across six campuses of the University System of Georgia. The school hired debris crews and asked FEMA to pay. FEMA said no to all of the debris costs in two project worksheets. The school appealed twice. It lost both times.

Image: AAAT3 Services
Mistake 1: Price was not part of the choice
The school picked its main contractor for skill and experience alone. Price was not a factor. FEMA expects price to count when public money is spent.
Mistake 2: Open-ended time and materials work
The contracts paid by the hour and had no cost ceiling. Federal rules allow this kind of contract only when no other type fits. The contract must also set a ceiling price, and the buyer must watch the work closely.
Mistake 3: A markup based on cost
The main contractor added 20 percent for overhead and profit on top of costs. FEMA treated this as a cost-plus-a-percentage-of-cost fee. That kind of fee is not allowed.
Mistake 4: Handshake deals and odd rates
One sub worked on a verbal deal at $110 an hour. Other rates came from insurance software. The school could not show these prices were fair.
Mistake 5: Weak monitoring
No one outside the haulers checked the work. Load tickets and monitoring logs were thin. The cost per cubic yard was also far above the middle cost for that disaster.
What to do instead
- Put price in your selection, and keep a record of how you chose.
- Use unit prices, like a price per cubic yard, when you can.
- If you must use time and materials, set a ceiling and watch the work.
- Never pay a percent of cost as profit.
- Get every deal in writing, including subs.
- Monitor every load and keep the tickets.
Need help on a disaster recovery job?
AAAT3 Services supports agencies, primes and contractors with federal contracting support and disaster response project management. Schedule a Consultation and tell us about your project.
Frequently asked questions
Can a city use a time and materials contract for debris removal?
Only after it decides no other contract type fits. The contract needs a ceiling price and close oversight.
What happens if the procurement rules are not followed?
FEMA can refuse to pay. In the appeal in this post, FEMA disallowed all of the debris costs.
Who checks the hauler's work?
The applicant must monitor the work. That includes load tickets and monitoring logs for every load.
Sources
- FEMA, Second Appeal: Debris Removal, Procurement (University System of Georgia Board of Regents, FEMA-4284-DR-GA, Hurricane Matthew) – FEMA appeal page – FEMA, checked 2026-10-17
- eCFR, 2 CFR 200.318 General procurement standards, paragraph (j) time-and-materials contracts – eCFR 2 CFR 200.318 – eCFR, checked 2026-10-17