Data center commissioning

Commissioning Support (Levels 1 to 5)

Commissioning is where a data center proves it works before the client trusts it with live load. AAAT3 supports and manages Levels 1 through 5, keeping testing safe, documented and on schedule from factory witness to integrated systems testing.

  • Level 1 to 5 support
  • IST safety plans
  • Load bank testing
  • Cx issue tracking
  • Test documentation

By the numbers

Why commissioning pays for itself

4.2 yrs

Median payback for commissioning new buildings, with 13% energy savings

Lawrence Berkeley National Lab, 2009 (643 buildings)
10,000+

Deficiencies found by commissioning, from data on only one third of the buildings studied

Lawrence Berkeley National Lab, 2009
0.4%

Median commissioning cost as a share of construction cost, about $1.16 per square foot

Lawrence Berkeley National Lab, 2009
49%

Drop in net commissioning cost once fewer equipment failures and change orders are counted

Lawrence Berkeley National Lab, 2009

What’s included

Commissioning support at every level

From the factory floor to full load, we keep the testing safe and the records complete.

01

Levels 1 and 2: factory and site checks

Problems found at the factory or on delivery cost far less to fix.

  • Factory witness test support
  • Delivery and installation inspections
  • Pre-functional checklists
  • Submittal and spec checks
Level 1 and 2 details →
02

Levels 3 and 4: startup and functional tests

Startup and functional tests put energized and rotating equipment in play.

  • Startup safety plans and LOTO
  • Functional performance test support
  • Load bank safety and setup
  • Test results logged and reviewed
Level 3 and 4 details →
03

Level 5: integrated systems testing

IST fails power and cooling on purpose. It must be planned to the minute.

  • IST scripts and safety review
  • Failure scenario walkthroughs
  • Roles, communication and stop rules
  • Issues tracked to closure before turnover
IST details →

Project management and consulting

Project management and consulting for commissioning

AAAT3 can manage the commissioning process for the owner, support your commissioning agent or keep the contractor side ready for testing.

Commissioning management

We coordinate the commissioning agent, contractors and owner so each level starts on time and finishes complete.

Best for: Owners who need one point of contact for Cx

Contractor Cx readiness

We get the contractor side ready: checklists done, gear started up and documents in order before testing.

Best for: GCs who want to pass Cx the first time

IST safety planning

Safety review of IST scripts, load bank setups and failure scenarios with clear stop rules.

Best for: Projects heading into Level 5 testing

Cx issue log management

We run the issues log, chase owners and verify fixes so nothing is open at turnover.

Best for: Projects with long open issue lists

Commissioning QC (USACE CQM)

Test records, inspections and documentation to federal QC standards.

Best for: Federal and military data centers

Retro-commissioning consulting

Testing and tuning of existing systems in operating facilities.

Best for: Older sites and expansions

How it works

From factory test to live load

L1 Factory

Witness tests at the factory.

L2 Install

Delivery and installation checks.

L3 Startup

Equipment startup and LOTO.

L4 Functional

System by system tests.

L5 IST

Integrated failure and load tests.

Turnover

Issues closed and records delivered.

Rule of thumb: no integrated systems test starts until every Level 4 issue is closed and every person on the floor knows the stop words.

Ways to work with us

Pick the level of support you need

Start small with a review, put a qualified person on site, or hand us the whole program. Every option is priced to your scope.

Quick start

Cx readiness review

A check of your checklists, startup plans and documents before testing.

  • Document review
  • Readiness walkdown
  • Gap list with fixes
  • Report in days
Request a review

Most popular

On-site Cx support

A qualified AAAT3 lead supporting testing on site.

  • Startup and IST safety
  • Issue log tracking
  • Test witness support
  • Daily reports
Get an on-site quote

Full program

Commissioning management

We manage the commissioning process from Level 1 to turnover.

  • Cx coordination
  • IST planning
  • Issue closure
  • Owner reporting
Talk to a project manager

What you get

Deliverables

Cx readiness checklist

What must be done before each level starts.

Startup safety plans

LOTO, roles and limits for each startup.

IST safety review

Scripts checked with stop rules and roles.

Issues log

Every issue tracked to verified closure.

Test records

Signed results ready for turnover.

Weekly Cx report

Progress, open issues and risks in plain language.

Standards

Codes and standards we work to

Commissioning

3
  • ASHRAE Guideline 0

    The commissioning processIndustry

  • ASHRAE Standard 202

    Commissioning process for buildings and systemsIndustry

  • NETA ATS

    Acceptance testing of electrical equipmentIndustry

Safety and federal

3
  • NFPA 70E

    Electrical safety in the workplaceIndustry

  • 29 CFR 1910.147

    Control of hazardous energyFederal

  • UFGS 01 91 00

    Commissioning for federal projectsFederal

FAQ

Common questions

What are the five levels of commissioning?

Level 1 is factory testing, Level 2 is delivery and installation checks, Level 3 is startup, Level 4 is functional testing of each system, and Level 5 is integrated systems testing of the whole facility.

What is integrated systems testing (IST)?

IST tests the whole data center together, often failing utility power or cooling on purpose to prove the backups take over without dropping load.

Is AAAT3 a commissioning agent?

We can manage the commissioning process for the owner, support your commissioning agent, or get the contractor side ready for testing.

Why does commissioning need safety planning?

Startup and IST put energized, rotating and pressurized equipment in play, often with load banks and many trades in the room. Each test needs a plan and stop rules.

Does commissioning really pay off?

A Lawrence Berkeley National Lab study of 643 buildings found a median payback of 4.2 years for new construction, before counting fewer failures and change orders.